ISEB-PM1 · Question #206
Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?
The correct answer is A. Work breakdown structure. A (Work Breakdown Structure) is correct because the WBS is the project management tool specifically designed to decompose project scope into manageable components - it starts by identifying major deliverables, determines whether cost estimates are feasible at each level, and…
Question
Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?
Options
- AWork breakdown structure
- BOrganizational breakdown structure
- CResource breakdown structure
- DBill of materials
How the community answered
(66 responses)- A71% (47)
- B9% (6)
- C5% (3)
- D15% (10)
Explanation
A (Work Breakdown Structure) is correct because the WBS is the project management tool specifically designed to decompose project scope into manageable components - it starts by identifying major deliverables, determines whether cost estimates are feasible at each level, and breaks deliverables down into tangible, measurable work packages.
B (Organizational Breakdown Structure) is wrong - an OBS maps work to organizational units/departments, not deliverables or cost estimation. C (Resource Breakdown Structure) is wrong - an RBS categorizes resources (people, equipment, materials) by type, not deliverables. D (Bill of Materials) is wrong - a BOM lists the components needed to manufacture a product; it's a procurement/manufacturing concept, not a project scope decomposition tool.
Memory tip: Think "WBS = What's Being Scheduled" - it answers what needs to be done by breaking the project into deliverables, which is exactly what cost estimation and tangible components are all about.