ISEB-PM1 · Question #205

On what is project baseline development established?

The correct answer is B. Estimated project cost and schedule. Project baseline development is established on estimated project cost and schedule (B) because a baseline represents the approved plan against which actual performance will be measured - it must be set before work begins, using forward-looking estimates, not actuals or…

Project Planning

Question

On what is project baseline development established?

Options

  • AApproved product requirements
  • BEstimated project cost and schedule
  • CActual project cost and schedule
  • DRevised project cost and schedule

How the community answered

(58 responses)
  • A
    5% (3)
  • B
    81% (47)
  • C
    3% (2)
  • D
    10% (6)

Explanation

Project baseline development is established on estimated project cost and schedule (B) because a baseline represents the approved plan against which actual performance will be measured - it must be set before work begins, using forward-looking estimates, not actuals or revisions.

  • A (Approved product requirements) is wrong because requirements define scope, not the baseline itself; the baseline encompasses the cost and schedule plan built around that scope.
  • C (Actual cost and schedule) is wrong because actuals are recorded during execution - you can't baseline something that hasn't been planned yet.
  • D (Revised cost and schedule) is wrong because revisions create a re-baseline, which is a corrective action, not the initial baseline establishment.

Memory tip: Think of a baseline as a "snapshot before you press play" - it's your estimate of what the project should cost and when it should finish, locked in so you can measure variance later.

Topics

#project baseline#cost estimate#schedule estimate#baseline development