CAPM · Question #527
A company is executing a critical project with many particular interests and impacts on quality. Which project artifact can be used to document who can influence the use of one kind of resource over…
The correct answer is D. Resource management plan. The Resource Management Plan is the correct artifact for documenting how resources are allocated, prioritized, and controlled on a project. It defines roles, responsibilities, and who has authority or influence over resource usage when conflicts arise. The project schedule…
Question
Options
- AProject schedule
- BRisk register
- CStakeholder register
- DResource management plan
How the community answered
(29 responses)- A3% (1)
- C3% (1)
- D93% (27)
Explanation
The Resource Management Plan is the correct artifact for documenting how resources are allocated, prioritized, and controlled on a project. It defines roles, responsibilities, and who has authority or influence over resource usage when conflicts arise. The project schedule shows timing of tasks, the risk register tracks risks, and the stakeholder register identifies stakeholders - none of these document resource authority or influence the way the resource management plan does.
Topics
Community Discussion
No community discussion yet for this question.