nerdexam
PMIPMI

CAPM · Question #527

CAPM Question #527: Real Exam Question with Answer & Explanation

The correct answer is D: Resource management plan. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A company is executing a critical project with many particular interests and impacts on quality. Which project artifact can be used to document who can influence the use of one kind of resource over another?

Options

  • AProject schedule
  • BRisk register
  • CStakeholder register
  • DResource management plan

Topics

#Resource Management#Project Planning#Project Artifacts#Roles and Responsibilities

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions