A conflict has occurred resulting from what the customer sees as missed requirements. Which of the following should be referred to address the problem?

The correct answer is B. Traceability matrix. A requirements traceability matrix (RTM) links each requirement back to its origin (business need, stakeholder request) and forward through design, development, and testing. When a customer claims requirements were missed, the RTM provides a clear, auditable record of every…

Predictive, Plan-Based Methodologies

Question

A conflict has occurred resulting from what the customer sees as missed requirements. Which of the following should be referred to address the problem?

Options

  • AStructured walkthrough
  • BTraceability matrix
  • CWork breakdown structure (WBS)
  • DFunctional testing results

How the community answered

(44 responses)
  • A
    14% (6)
  • B
    77% (34)
  • C
    7% (3)
  • D
    2% (1)

Explanation

A requirements traceability matrix (RTM) links each requirement back to its origin (business need, stakeholder request) and forward through design, development, and testing. When a customer claims requirements were missed, the RTM provides a clear, auditable record of every agreed-upon requirement, its current status, and whether it was addressed in the project deliverables. This resolves disputes objectively by showing what was captured, accepted, and tracked. A structured walkthrough (A) is a peer review technique. The WBS (C) shows scope decomposition, not requirement agreements. Functional testing results (D) show test outcomes but not whether the requirement was ever formally agreed upon.

Topics

#Requirements management#Traceability matrix#Scope management#Project documentation