nerdexam
PMIPMI

CAPM · Question #521

CAPM Question #521: Real Exam Question with Answer & Explanation

The correct answer is C: Implement Appropriate Response. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Since the risk has already been identified (supplier delays and cost increases due to safety regulations) and the team has already determined a response strategy (absorbing the cost by reducing lag in tasks), the next step is to implement the response. This involves: - Adjusting the schedule to reduce lag where possible. - Monitoring supplier performance. - Managing budget adjustments accordingly. Which of the following describes how this situation is managed?

Options

  • APerform Quantitative Risk Analysis
  • BPlan Project Risk Management
  • CImplement Appropriate Response
  • DPerform Qualitative Risk Analysis

Topics

#Risk Management#Implement Risk Responses#Project Execution

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions