Question

The project manager needs to obtain proposals on costs of supplies purchased from an external source. In order to conduct this in a fair and unbiased way, what should the project manager conduct?

Options

  • AProcurement conference
  • BStakeholder meeting
  • CStakeholder conference
  • DBidder conference

Topics

#Project Procurement Management#Bidder Conference#Conduct Procurements#Solicitation