CAPM · Question #520
CAPM Question #520: Real Exam Question with Answer & Explanation
The correct answer is D: Bidder conference. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
The project manager needs to obtain proposals on costs of supplies purchased from an external source. In order to conduct this in a fair and unbiased way, what should the project manager conduct?
Options
- AProcurement conference
- BStakeholder meeting
- CStakeholder conference
- DBidder conference
Topics
#Project Procurement Management#Bidder Conference#Conduct Procurements#Solicitation