CAPM · Question #517

A project is in the planning phase and ready for plan review and approval when a sponsor switch happens. What should the next course of action be?

The correct answer is C. Plan Stakeholder Engagement. A sponsor switch introduces a new key stakeholder whose interests, expectations, and level of engagement are unknown. Before proceeding with plan review and approval, the project manager must update the stakeholder register and re-plan stakeholder engagement to understand how…

Predictive, Plan-Based Methodologies

Question

A project is in the planning phase and ready for plan review and approval when a sponsor switch happens. What should the next course of action be?

Options

  • APlan Communications Management
  • BPerform Qualitative Risk Analysis
  • CPlan Stakeholder Engagement
  • DPerform Integrated Change Control

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    12% (4)
  • C
    79% (26)
  • D
    6% (2)

Explanation

A sponsor switch introduces a new key stakeholder whose interests, expectations, and level of engagement are unknown. Before proceeding with plan review and approval, the project manager must update the stakeholder register and re-plan stakeholder engagement to understand how the new sponsor wants to be involved and communicated with. Skipping this step risks proceeding with a plan the new sponsor may not support or approve. Performing risk analysis or integrated change control is premature-there is no change request yet. Communications planning follows stakeholder engagement planning, not the other way around.

Topics

#Stakeholder Management#Sponsor Engagement#Planning Process Group#Stakeholder Engagement Planning