PMIPMI
CAPM · Question #518
CAPM Question #518: Real Exam Question with Answer & Explanation
The correct answer is B: Identify possible reasons for the delay and consult the risk register for corrective actions.. See the full explanation below for the reasoning.
Agile Frameworks/Methodologies
Question
In the last two iterations, a project team failed to deliver all of the stories on time. What should the project manager do first in order to prevent this from reoccurring?
Options
- AExtend the delivery time for the product since the management reserve allows it.
- BIdentify possible reasons for the delay and consult the risk register for corrective actions.
- CObserve the project team's performance for the next two iterations before taking any action.
- DTemporarily use another team for the next iteration and evaluate their performance.
Topics
#Risk Management#Problem Solving#Continuous Improvement#Agile Practices
Community Discussion
No community discussion yet for this question.