nerdexam
PMIPMI

CAPM · Question #518

CAPM Question #518: Real Exam Question with Answer & Explanation

The correct answer is B: Identify possible reasons for the delay and consult the risk register for corrective actions.. See the full explanation below for the reasoning.

Agile Frameworks/Methodologies

Question

In the last two iterations, a project team failed to deliver all of the stories on time. What should the project manager do first in order to prevent this from reoccurring?

Options

  • AExtend the delivery time for the product since the management reserve allows it.
  • BIdentify possible reasons for the delay and consult the risk register for corrective actions.
  • CObserve the project team's performance for the next two iterations before taking any action.
  • DTemporarily use another team for the next iteration and evaluate their performance.

Topics

#Risk Management#Problem Solving#Continuous Improvement#Agile Practices

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions