The correct answer is B: Data analysis, audits, and meetings. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Which tools and techniques should a project manager use to monitor risks?

Options

  • AExpert judgment, data analysis, and interpersonal and team skills
  • BData analysis, audits, and meetings
  • CExpert judgment, audits, and decision making
  • DMeetings, data gathering, and expert judgment

Topics

#Risk Management#Monitor Risks process#Tools and Techniques#Project Monitoring