CAPM · Question #450
What is the key benefit of the Monitor Stakeholder Engagement process?
The correct answer is D. Maintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves. Each PMBOK process has a defined key benefit. The Monitor Stakeholder Engagement process is about tracking stakeholder relationships and adjusting engagement strategies as the project changes over time. Its key benefit is that it maintains or increases the efficiency and effectiv
Question
Options
- AEnsures that the informational needs of the project and its stakeholders are met through implementation and the development of artifacts
- BEnsures that the project includes all the work required and only the work required-to complete the project successfully
- CIncreases the probability and/or impact of positive risks, and decreases the probability and/or impact of negative risks or issues
- DMaintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves
How the community answered
(26 responses)- A4% (1)
- D96% (25)
Explanation
Each PMBOK process has a defined key benefit. The Monitor Stakeholder Engagement process is about tracking stakeholder relationships and adjusting engagement strategies as the project changes over time. Its key benefit is that it maintains or increases the efficiency and effectiveness of stakeholder engagement as the project evolves - recognizing that stakeholder needs and influence shift throughout the project lifecycle. The other options describe benefits of different processes: option A fits Manage Communications, option B fits Validate/Control Scope, and option C fits Risk Response Planning.
Topics
Community Discussion