CAPM · Question #450

CAPM Question #450: Real Exam Question with Answer & Explanation

The correct answer is D: Maintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

What is the key benefit of the Monitor Stakeholder Engagement process?

Options

  • AEnsures that the informational needs of the project and its stakeholders are met through implementation and the development of artifacts
  • BEnsures that the project includes all the work required and only the work required-to complete the project successfully
  • CIncreases the probability and/or impact of positive risks, and decreases the probability and/or impact of negative risks or issues
  • DMaintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves

Topics

#Stakeholder Management#Monitor Stakeholder Engagement#PMBOK Processes#Monitoring and Controlling