CAPM · Question #45

The project manager is working with some functional managers and stakeholders on the resource management plan. Which elements may be included in this plan?

The correct answer is C. Team roles and responsibilities, team management, and training plan. The resource management plan addresses how project resources will be acquired, allocated, managed, and released. Its key components include team roles and responsibilities (who does what), team management approaches (how the team will be directed and controlled), and a training…

Predictive, Plan-Based Methodologies

Question

The project manager is working with some functional managers and stakeholders on the resource management plan. Which elements may be included in this plan?

Options

  • ATeam values, team agreements, and conflict resolution process
  • BConflict resolution process, communication guidelines, and meeting schedules
  • CTeam roles and responsibilities, team management, and training plan
  • DResource requirements, resource assignments, and team performance assessments

How the community answered

(35 responses)
  • B
    3% (1)
  • C
    94% (33)
  • D
    3% (1)

Explanation

The resource management plan addresses how project resources will be acquired, allocated, managed, and released. Its key components include team roles and responsibilities (who does what), team management approaches (how the team will be directed and controlled), and a training plan (how skills gaps will be addressed). Items like resource assignments and team performance assessments are outputs of other processes (e.g., Acquire Resources, Manage Team), not components of the plan itself.

Topics

#Resource Management Plan#Team Roles#Training Plan#Project Planning