The project manager is working with some functional managers and stakeholders on the resource management plan. Which elements may be included in this plan?

Options

  • ATeam values, team agreements, and conflict resolution process
  • BConflict resolution process, communication guidelines, and meeting schedules
  • CTeam roles and responsibilities, team management, and training plan
  • DResource requirements, resource assignments, and team performance assessments

Topics

#Resource Management Plan#Team Roles#Training Plan#Project Planning