CAPM · Question #45
CAPM Question #45: Real Exam Question with Answer & Explanation
The correct answer is C: Team roles and responsibilities, team management, and training plan. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
The project manager is working with some functional managers and stakeholders on the resource management plan. Which elements may be included in this plan?
Options
- ATeam values, team agreements, and conflict resolution process
- BConflict resolution process, communication guidelines, and meeting schedules
- CTeam roles and responsibilities, team management, and training plan
- DResource requirements, resource assignments, and team performance assessments
Topics
#Resource Management Plan#Team Roles#Training Plan#Project Planning