Project Management Fundamentals and Core Concepts
Question
A new project manager wishes to recommend creating a project management office to senior management. Which statement would the project manager use to describe the importance of creating the project management office?
Options
- AIt will give the project manager independence to make decisions without other departmental input.
- BIt integrates organizational data and information to ensure that strategic objectives are fulfilled.
- CThe project management office can execute administrative tasks.
- DThe project management office can coordinate projects.