CAPM · Question #46

CAPM Question #46: Real Exam Question with Answer & Explanation

The correct answer is B: It integrates organizational data and information to ensure that strategic objectives are fulfilled.. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

A new project manager wishes to recommend creating a project management office to senior management. Which statement would the project manager use to describe the importance of creating the project management office?

Options

  • AIt will give the project manager independence to make decisions without other departmental input.
  • BIt integrates organizational data and information to ensure that strategic objectives are fulfilled.
  • CThe project management office can execute administrative tasks.
  • DThe project management office can coordinate projects.

Topics

#Project Management Office (PMO)#Strategic Alignment#Organizational Strategy#Project Governance