CAPM · Question #441
CAPM Question #441: Real Exam Question with Answer & Explanation
The correct answer is A: Add the stakeholder to the communications management plan.. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
A product owner reviews the list of stakeholders to confirm their continued involvement with the product team. A new stakeholder is identified as actively involved in the next product release. What should the project manager do next to engage the new stakeholder?
Options
- AAdd the stakeholder to the communications management plan.
- BConduct a one-on-one interview with the stakeholder.
- CInvite the stakeholder to the sprint-planning meeting.
- DSend the stakeholder a questionnaire.
Topics
#Stakeholder Management#Communications Management Plan#Project Planning#Stakeholder Engagement