CAPM · Question #441

CAPM Question #441: Real Exam Question with Answer & Explanation

The correct answer is A: Add the stakeholder to the communications management plan.. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A product owner reviews the list of stakeholders to confirm their continued involvement with the product team. A new stakeholder is identified as actively involved in the next product release. What should the project manager do next to engage the new stakeholder?

Options

  • AAdd the stakeholder to the communications management plan.
  • BConduct a one-on-one interview with the stakeholder.
  • CInvite the stakeholder to the sprint-planning meeting.
  • DSend the stakeholder a questionnaire.

Topics

#Stakeholder Management#Communications Management Plan#Project Planning#Stakeholder Engagement