The correct answer is B: Plan Quality Management. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
What process is used to identify quality requirements and/or standards for a project and its deliverables?
Options
- AManage Quality
- BPlan Quality Management
- CControl Quality
- DPerform Qualitative Risk Analysis
Topics
#Quality Management#Project Planning#Plan Quality Management