What process is used to identify quality requirements and/or standards for a project and its deliverables?
The correct answer is B. Plan Quality Management. Plan Quality Management is the process of identifying quality requirements and standards for the project and its deliverables, and documenting how the project will demonstrate compliance. It produces the Quality Management Plan. Manage Quality (formerly Perform Quality Assurance)
Question
Options
- AManage Quality
- BPlan Quality Management
- CControl Quality
- DPerform Qualitative Risk Analysis
How the community answered
(44 responses)- A2% (1)
- B89% (39)
- C7% (3)
- D2% (1)
Explanation
Plan Quality Management is the process of identifying quality requirements and standards for the project and its deliverables, and documenting how the project will demonstrate compliance. It produces the Quality Management Plan. Manage Quality (formerly Perform Quality Assurance) executes the quality activities defined in the plan. Control Quality measures specific deliverables against quality standards. Perform Qualitative Risk Analysis is a risk management process entirely, not related to identifying quality requirements.
Topics
Community Discussion
No community discussion yet for this question.