What process group includes processes performed to complete work to satisfy the project requirements defined in the project management plan?
The correct answer is B. Executing. The Executing Process Group contains the processes performed to complete the work defined in the project management plan to satisfy project requirements. This is where the actual deliverables are produced and project resources are coordinated. The Planning Process Group defines…
Question
Options
- AInitiating
- BExecuting
- CMonitoring and Controlling
- DPlanning
How the community answered
(46 responses)- A7% (3)
- B89% (41)
- C2% (1)
- D2% (1)
Explanation
The Executing Process Group contains the processes performed to complete the work defined in the project management plan to satisfy project requirements. This is where the actual deliverables are produced and project resources are coordinated. The Planning Process Group defines how the work will be done. The Monitoring and Controlling Process Group tracks, reviews, and regulates progress. The Initiating Process Group authorizes and defines the project or a new phase.
Topics
Community Discussion
No community discussion yet for this question.