CAPM · Question #425
In addition to the project charter, what other artifact is produced as a result of the Develop Project Charter process?
The correct answer is A. Assumption log. Per the PMBOK Guide (6th edition), the Develop Project Charter process has two outputs: the Project Charter and the Assumption Log. The assumption log captures all high-level assumptions and constraints identified during project initiation. The business case (C) and agreements ar
Question
Options
- AAssumption log
- BMilestone list
- CBusiness case
- DRisk register
How the community answered
(40 responses)- A88% (35)
- B3% (1)
- C3% (1)
- D8% (3)
Explanation
Per the PMBOK Guide (6th edition), the Develop Project Charter process has two outputs: the Project Charter and the Assumption Log. The assumption log captures all high-level assumptions and constraints identified during project initiation. The business case (C) and agreements are inputs to this process, not outputs. The milestone list (B) is an output of the Define Activities process. The risk register (D) is created during the Identify Risks process. The assumption log was explicitly added as a formal output in PMBOK 6 to emphasize the importance of tracking assumptions from the very start.
Topics
Community Discussion
No community discussion yet for this question.