CAPM · Question #425

CAPM Question #425: Real Exam Question with Answer & Explanation

The correct answer is A: Assumption log. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

In addition to the project charter, what other artifact is produced as a result of the Develop Project Charter process?

Options

  • AAssumption log
  • BMilestone list
  • CBusiness case
  • DRisk register

Topics

#Develop Project Charter#Project Charter#Assumption Log#Integration Management