In addition to the project charter, what other artifact is produced as a result of the Develop Project Charter process?

The correct answer is A. Assumption log. Per the PMBOK Guide (6th edition), the Develop Project Charter process has two outputs: the Project Charter and the Assumption Log. The assumption log captures all high-level assumptions and constraints identified during project initiation. The business case (C) and agreements ar

Predictive, Plan-Based Methodologies

Question

In addition to the project charter, what other artifact is produced as a result of the Develop Project Charter process?

Options

  • AAssumption log
  • BMilestone list
  • CBusiness case
  • DRisk register

How the community answered

(40 responses)
  • A
    88% (35)
  • B
    3% (1)
  • C
    3% (1)
  • D
    8% (3)

Explanation

Per the PMBOK Guide (6th edition), the Develop Project Charter process has two outputs: the Project Charter and the Assumption Log. The assumption log captures all high-level assumptions and constraints identified during project initiation. The business case (C) and agreements are inputs to this process, not outputs. The milestone list (B) is an output of the Define Activities process. The risk register (D) is created during the Identify Risks process. The assumption log was explicitly added as a formal output in PMBOK 6 to emphasize the importance of tracking assumptions from the very start.

Topics

#Develop Project Charter#Project Charter#Assumption Log#Integration Management