CAPM Question #424: Real Exam Question with Answer & Explanation
The correct answer is B: Norming. See the full explanation below for the reasoning.
Project Management Fundamentals and Core Concepts
Question
A newly developed project team is working together, building trust and adjusting its work habits to support the team What stage of the Tuckman ladder does this describe?
Options
- AForming
- BNorming
- CStorming
- DPerforming
Topics
#Tuckman's Stages#Team Development#Project Team Management#Group Dynamics