nerdexam
PMI

CAPM · Question #423

What is an emerging practice in stakeholder engagement?

The correct answer is A. Confirming that all identified stakeholders are engaged and actually affected by the work. An emerging practice in stakeholder engagement, as recognized in the PMBOK Guide, is actively verifying that all identified stakeholders are genuinely engaged and truly affected by the project work-moving beyond simply listing stakeholders to validating actual involvement and…

Project Management Fundamentals and Core Concepts

Question

What is an emerging practice in stakeholder engagement?

Options

  • AConfirming that all identified stakeholders are engaged and actually affected by the work
  • BAssuring that team leadership is primarily involved in stakeholder engagement
  • CConfirming that stakeholders do not change after stakeholder identification
  • DEnsuring that stakeholders most affected by the work are involved as collaborative team partners

How the community answered

(37 responses)
  • A
    89% (33)
  • B
    5% (2)
  • C
    3% (1)
  • D
    3% (1)

Explanation

An emerging practice in stakeholder engagement, as recognized in the PMBOK Guide, is actively verifying that all identified stakeholders are genuinely engaged and truly affected by the project work-moving beyond simply listing stakeholders to validating actual involvement and impact. Option B is incorrect because engagement should not be limited to team leadership. Option C is incorrect because stakeholder lists do change over a project's life. Option D describes a good practice but relates more to co-creation approaches than to a specifically identified emerging practice.

Topics

#Stakeholder Engagement#Stakeholder Management#Emerging Practices

Community Discussion

No community discussion yet for this question.

Full CAPM Practice