A project stakeholder is requesting changes to the project plan. Which process group addresses this?

The correct answer is D. Monitoring and Controlling Process Group. Change requests to the project plan are handled through the Monitoring and Controlling Process Group, specifically through the Perform Integrated Change Control process. This process group continuously tracks, reviews, and regulates project progress and performance, and manages c

Predictive, Plan-Based Methodologies

Question

A project stakeholder is requesting changes to the project plan. Which process group addresses this?

Options

  • AInitiating Process Group
  • BPlanning Process Group
  • CExecuting Process Group
  • DMonitoring and Controlling Process Group

How the community answered

(42 responses)
  • A
    5% (2)
  • C
    2% (1)
  • D
    93% (39)

Explanation

Change requests to the project plan are handled through the Monitoring and Controlling Process Group, specifically through the Perform Integrated Change Control process. This process group continuously tracks, reviews, and regulates project progress and performance, and manages change requests. Even if changes originate during execution, they must be formally reviewed and approved or rejected through Monitoring and Controlling before being implemented.

Topics

#Change Management#Project Process Groups#Monitoring and Controlling Process Group