CAPM · Question #41
For what protect management process is work performance information an output?
The correct answer is C. Monitor Stakeholder Engagement. Work performance information is an output of Monitor Stakeholder Engagement. In this process, raw work performance data is analyzed and transformed into work performance information - such as whether stakeholder engagement levels are appropriate compared to the plan. This…
Question
Options
- AImplement Risk Responses
- BPlan Stakeholder Engagement
- CMonitor Stakeholder Engagement
- DPlan Quality Management
How the community answered
(30 responses)- B3% (1)
- C93% (28)
- D3% (1)
Explanation
Work performance information is an output of Monitor Stakeholder Engagement. In this process, raw work performance data is analyzed and transformed into work performance information - such as whether stakeholder engagement levels are appropriate compared to the plan. This output is then used to make decisions and take corrective actions. It is important not to confuse work performance data (raw observations) with work performance information (analyzed, contextualized data).
Topics
Community Discussion
No community discussion yet for this question.