The correct answer is A: Subsidiary management plans are mandatory for any project. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Which of these statements is true of subsidiary management plans?
Options
- ASubsidiary management plans are mandatory for any project
- BSubsidiary management plans use the project charter as input
- CSubsidiary management plans can be independently managed
- DSubsidiary management plans do not need regular updates
Topics
#Subsidiary Management Plans#Project Management Plan#PMBOK Planning#Planning Process Group