CAPM · Question #409

CAPM Question #409: Real Exam Question with Answer & Explanation

The correct answer is C: Completing pre-project work. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

Development of the benefits management plan occurs in which stage of the project life cycle?

Options

  • AStarting the project
  • BOrganizing the project
  • CCompleting pre-project work
  • DExecuting the product

Topics

#Benefits Management Plan#Pre-project Activities#Project Life Cycle#Project Initiation