Development of the benefits management plan occurs in which stage of the project life cycle?
The correct answer is C. Completing pre-project work. The benefits management plan is developed during pre-project work - before the project is formally authorized or initiated. It documents how and when the project's intended benefits will be delivered, measured, and sustained after project completion. This pre-project document…
Question
Options
- AStarting the project
- BOrganizing the project
- CCompleting pre-project work
- DExecuting the product
How the community answered
(14 responses)- A7% (1)
- B7% (1)
- C86% (12)
Explanation
The benefits management plan is developed during pre-project work - before the project is formally authorized or initiated. It documents how and when the project's intended benefits will be delivered, measured, and sustained after project completion. This pre-project document, along with the business case, is used to justify and authorize the project. It is not created during project startup (initiating), organizing (planning), or execution - it must exist beforehand to help stakeholders decide whether the project is worth pursuing.
Topics
Community Discussion
No community discussion yet for this question.