PMIPMI
CAPM · Question #400
CAPM Question #400: Real Exam Question with Answer & Explanation
The correct answer is A: The correctness of a deliverable. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
What does 'verified' in verified deliverable represent?
Options
- AThe correctness of a deliverable
- BThe completeness of a deliverable
- CThe deliverable requirements
- DThe customer acceptance of a deliverable
Topics
#Verified Deliverable#Quality Control#Project Quality Management#Control Quality Process
Community Discussion
No community discussion yet for this question.