The project manager is working in the Resource Management process. Which items may the project manager need to include in the team charter?

Options

  • ACultural norms, roles and responsibilities, and organizational chart
  • BAssumption logs, resource calendars and training schedule
  • CCommunication guidelines, conflict resolution process, and team agreements
  • DCompany policies, recognition plan, and roles and responsibilities

Topics

#Team Charter#Resource Management#Team Agreements#Team Development