The project manager is working in the Resource Management process. Which items may the project manager need to include in the team charter?
The correct answer is C. Communication guidelines, conflict resolution process, and team agreements. According to PMBOK 6th Edition, a team charter is a document that establishes team values and working agreements. Its typical components include: team values, communication guidelines, decision-making criteria, conflict resolution processes, meeting guidelines, and team agreement
Question
Options
- ACultural norms, roles and responsibilities, and organizational chart
- BAssumption logs, resource calendars and training schedule
- CCommunication guidelines, conflict resolution process, and team agreements
- DCompany policies, recognition plan, and roles and responsibilities
How the community answered
(28 responses)- A4% (1)
- B4% (1)
- C93% (26)
Explanation
According to PMBOK 6th Edition, a team charter is a document that establishes team values and working agreements. Its typical components include: team values, communication guidelines, decision-making criteria, conflict resolution processes, meeting guidelines, and team agreements. Option A includes the organizational chart, which is a separate project management artifact. Option B lists assumption logs and resource calendars, which are separate project documents. Option D includes company policies, which are enterprise environmental factors, not team charter components. Option C best reflects the interpersonal and behavioral agreements captured in a team charter.