PMIPMI
CAPM · Question #399
CAPM Question #399: Real Exam Question with Answer & Explanation
The correct answer is C: Communication guidelines, conflict resolution process, and team agreements. See the full explanation below for the reasoning.
Project Management Fundamentals and Core Concepts
Question
The project manager is working in the Resource Management process. Which items may the project manager need to include in the team charter?
Options
- ACultural norms, roles and responsibilities, and organizational chart
- BAssumption logs, resource calendars and training schedule
- CCommunication guidelines, conflict resolution process, and team agreements
- DCompany policies, recognition plan, and roles and responsibilities
Topics
#Team Charter#Resource Management#Team Agreements#Team Development