PMIPMI
CAPM · Question #398
CAPM Question #398: Real Exam Question with Answer & Explanation
The correct answer is B: Identify, analyze, and manage risk during each iteration of the project. See the full explanation below for the reasoning.
Agile Frameworks/Methodologies
Question
Which additional considerations should the project manager make when managing risks in an agile/adaptive project?
Options
- AAdd more risk categories
- BIdentify, analyze, and manage risk during each iteration of the project
- CAdd new values to the probability and impact matrix
- DIncrease the reserves because of the high variability environment
Topics
#Risk Management#Agile Risk#Iterative Processes#Adaptive Frameworks
Community Discussion
No community discussion yet for this question.