nerdexam
PMIPMI

CAPM · Question #398

CAPM Question #398: Real Exam Question with Answer & Explanation

The correct answer is B: Identify, analyze, and manage risk during each iteration of the project. See the full explanation below for the reasoning.

Agile Frameworks/Methodologies

Question

Which additional considerations should the project manager make when managing risks in an agile/adaptive project?

Options

  • AAdd more risk categories
  • BIdentify, analyze, and manage risk during each iteration of the project
  • CAdd new values to the probability and impact matrix
  • DIncrease the reserves because of the high variability environment

Topics

#Risk Management#Agile Risk#Iterative Processes#Adaptive Frameworks

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions