Which additional considerations should the project manager make when managing risks in an agile/adaptive project?

The correct answer is B. Identify, analyze, and manage risk during each iteration of the project. In agile and adaptive environments, risk management is not a one-time upfront activity - it is continuous and iterative. Risks are identified, analyzed, and managed during every iteration (sprint/cycle) because the adaptive nature of agile projects means new risks can emerge and

Agile Frameworks/Methodologies

Question

Which additional considerations should the project manager make when managing risks in an agile/adaptive project?

Options

  • AAdd more risk categories
  • BIdentify, analyze, and manage risk during each iteration of the project
  • CAdd new values to the probability and impact matrix
  • DIncrease the reserves because of the high variability environment

How the community answered

(19 responses)
  • B
    89% (17)
  • C
    5% (1)
  • D
    5% (1)

Explanation

In agile and adaptive environments, risk management is not a one-time upfront activity - it is continuous and iterative. Risks are identified, analyzed, and managed during every iteration (sprint/cycle) because the adaptive nature of agile projects means new risks can emerge and existing risks can change rapidly. Adding more risk categories (A) or new probability/impact matrix values (C) are not agile-specific considerations. Increasing reserves (D) is not a standard agile adaptation either, as agile environments use other mechanisms like backlogs and velocity to manage variability.

Topics

#Risk Management#Agile Risk#Iterative Processes#Adaptive Frameworks