CAPM · Question #394
CAPM Question #394: Real Exam Question with Answer & Explanation
The correct answer is A: Project management plan, data gathering, and stakeholder engagement plan. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Which of the following answers includes an input, a technique, and an output of the Plan Stakeholders Engagement process?
Options
- AProject management plan, data gathering, and stakeholder engagement plan
- BBusiness documents, meetings, and stakeholder register
- COrganizational process assets, data gathering, and project document updates
- DProject management plan, data analysis, and change requests
Topics
#Stakeholder Management#Planning Process Group#ITTOs#Project Management Processes