CAPM · Question #394

CAPM Question #394: Real Exam Question with Answer & Explanation

The correct answer is A: Project management plan, data gathering, and stakeholder engagement plan. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Which of the following answers includes an input, a technique, and an output of the Plan Stakeholders Engagement process?

Options

  • AProject management plan, data gathering, and stakeholder engagement plan
  • BBusiness documents, meetings, and stakeholder register
  • COrganizational process assets, data gathering, and project document updates
  • DProject management plan, data analysis, and change requests

Topics

#Stakeholder Management#Planning Process Group#ITTOs#Project Management Processes