CAPM · Question #394
Which of the following answers includes an input, a technique, and an output of the Plan Stakeholders Engagement process?
The correct answer is A. Project management plan, data gathering, and stakeholder engagement plan. The Plan Stakeholder Engagement process has specific ITTOs. The project management plan is an input, data gathering is a tool and technique, and the stakeholder engagement plan is the primary output. This makes option A a valid input–technique–output triplet. Option B includes 's
Question
Options
- AProject management plan, data gathering, and stakeholder engagement plan
- BBusiness documents, meetings, and stakeholder register
- COrganizational process assets, data gathering, and project document updates
- DProject management plan, data analysis, and change requests
How the community answered
(36 responses)- A92% (33)
- C3% (1)
- D6% (2)
Explanation
The Plan Stakeholder Engagement process has specific ITTOs. The project management plan is an input, data gathering is a tool and technique, and the stakeholder engagement plan is the primary output. This makes option A a valid input–technique–output triplet. Option B includes 'stakeholder register' which is an input, not an output of this process. Option C has OPA (input) and data gathering (technique) but 'project document updates' is a secondary output - the primary and defining output is the stakeholder engagement plan. Option D lists 'change requests' which is not an output of Plan Stakeholder Engagement.