CAPM · Question #393

Agile release planning provides a high-level summary timeline of the release schedule based on.

The correct answer is C. Product roadmap and the product vision. Agile release planning provides a high-level summary timeline based on the product roadmap and the product vision. The product vision defines the overall goal of the product, while the product roadmap outlines the planned evolution over time. These two strategic artifacts drive r

Agile Frameworks/Methodologies

Question

Agile release planning provides a high-level summary timeline of the release schedule based on.

Options

  • AActivities and story points
  • BIteration and prioritization plans
  • CProduct roadmap and the product vision
  • DTasks and user stories

How the community answered

(32 responses)
  • A
    3% (1)
  • C
    94% (30)
  • D
    3% (1)

Explanation

Agile release planning provides a high-level summary timeline based on the product roadmap and the product vision. The product vision defines the overall goal of the product, while the product roadmap outlines the planned evolution over time. These two strategic artifacts drive release scheduling at a high level. Activities and story points (A) and tasks and user stories (D) are iteration-level details, not the basis for high-level release timelines. Iteration and prioritization plans (B) are also more tactical and occur after release planning has been established.

Topics

#Agile Release Planning#Product Roadmap#Product Vision#Agile Planning