Question
At what stages of project should the Identify Stakeholder process be performed?
Options
- AWhen beginning each phase of the project
- BAt the beginning of the project only
- COnly when the project manager is concerned about stakeholder satisfaction
- DWhen the project charter is produced, at the beginning of each phase, and when significant changes occur
Topics
#Identify Stakeholders#Stakeholder Management#Project Phases#Project Lifecycle