nerdexam
PMI

CAPM · Question #381

Which are the competing constrains that project manager should address when tailoring a project?

The correct answer is A. Cost, scope, schedule. The three primary competing constraints a project manager must balance when tailoring a project are cost, scope, and schedule - the classic triple constraint or iron triangle.

Project Management Fundamentals and Core Concepts

Question

Which are the competing constrains that project manager should address when tailoring a project?

Options

  • ACost, scope, schedule
  • BSponsorship, risk, quality
  • CSchedule, sponsorship, scope
  • DResources, Quality, Communication

How the community answered

(27 responses)
  • A
    93% (25)
  • B
    4% (1)
  • D
    4% (1)

Why each option

The three primary competing constraints a project manager must balance when tailoring a project are cost, scope, and schedule - the classic triple constraint or iron triangle.

ACost, scope, scheduleCorrect

Cost, scope, and schedule form the foundational triple constraint of project management. When tailoring a project, the project manager must explicitly balance these three interdependent factors because changing any one directly impacts the others - increasing scope without adjusting cost or schedule, for example, creates an imbalance that must be managed through deliberate trade-off decisions.

BSponsorship, risk, quality

Sponsorship is a governance factor, not a competing project constraint - and while risk matters, it does not replace cost as one of the three primary constraints.

CSchedule, sponsorship, scope

Sponsorship is not a recognized competing constraint in the triple constraint model; it should be replaced by cost, which is one of the three primary factors.

DResources, Quality, Communication

Resources, quality, and communication are important project management areas but are not the three primary competing constraints used as the basis for tailoring trade-off decisions.

Concept tested: Triple constraint in project tailoring

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Project Constraints#Triple Constraint#Project Tailoring

Community Discussion

No community discussion yet for this question.

Full CAPM Practice