What can a project manager review to understand the status of project?
The correct answer is B. Quality and technical performance measures. Quality and technical performance measures are used to assess how the project is currently performing against defined targets and standards. They provide real-time status information - showing whether deliverables meet quality criteria and whether technical objectives are being a
Question
Options
- AWork breakdown structure (WBS) status
- BQuality and technical performance measures
- CCost and scope baselines
- DBusiness case completeness
How the community answered
(16 responses)- B88% (14)
- C6% (1)
- D6% (1)
Explanation
Quality and technical performance measures are used to assess how the project is currently performing against defined targets and standards. They provide real-time status information - showing whether deliverables meet quality criteria and whether technical objectives are being achieved. Option A (WBS status) describes the scope structure, not current performance. Option C (cost and scope baselines) are planning benchmarks, not status indicators - they're what you compare against, not what you review to see current status. Option D (business case completeness) is typically evaluated at project initiation and approval, not during execution to monitor status.
Topics
Community Discussion
No community discussion yet for this question.