CAPM Question #368: Real Exam Question with Answer & Explanation

The correct answer is B: Manage Communications. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Which project management process is used by the project manager to ensure that stakeholders receive timely and relevant information?

Options

  • APlan Communications Management
  • BManage Communications
  • CMonitor Communications
  • DDevelop Project Management Plan

Topics

#Communications Management#Project Processes#Stakeholder Communication

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions