CAPM · Question #354

Which can be used to convert a verified deliverable to an accepted deliverable?

The correct answer is C. Voting. In the Validate Scope process, verified deliverables (outputs from Control Quality, confirmed to meet quality requirements) are presented to stakeholders for formal acceptance. Voting is a decision-making technique used in this process to reach group consensus on whether a delive

Predictive, Plan-Based Methodologies

Question

Which can be used to convert a verified deliverable to an accepted deliverable?

Exhibit

CAPM question #354 exhibit

Options

  • ADecomposition
  • BReporting
  • CVoting
  • DBrainstorming

How the community answered

(28 responses)
  • A
    7% (2)
  • C
    89% (25)
  • D
    4% (1)

Explanation

In the Validate Scope process, verified deliverables (outputs from Control Quality, confirmed to meet quality requirements) are presented to stakeholders for formal acceptance. Voting is a decision-making technique used in this process to reach group consensus on whether a deliverable satisfies the acceptance criteria, converting it into an accepted deliverable. Decomposition (A) is a planning technique used to break down scope. Reporting (B) is a communication activity. Brainstorming (D) is an idea-generation technique. None of those three facilitate the formal acceptance decision that transforms a verified deliverable into an accepted one.

Topics

#Validate Scope#Deliverable Acceptance#Group Decision-Making#Project Scope Management