The correct answer is A: Identify the key stakeholders and keep them informed at all times.. See the full explanation below for the reasoning.
Project Management Fundamentals and Core Concepts
Question
Which actions should a project manager follow to manage stakeholders?
Options
- AIdentify the key stakeholders and keep them informed at all times.
- BIdentify the stakeholders, planning, managing and monitoring their engagement
- CMeet and keep informed any people related to the project at all times
- DIdentify the stakeholders and monitor their level of satisfaction
Topics
#stakeholder management#stakeholder identification#communication management#stakeholder engagement