Which actions should a project manager follow to manage stakeholders?
The correct answer is A. Identify the key stakeholders and keep them informed at all times. The most critical stakeholder management actions a project manager must take are identifying the key stakeholders and ensuring they are consistently kept informed throughout the project lifecycle. This establishes the foundation for trust, buy-in, and effective decision-making…
Question
Options
- AIdentify the key stakeholders and keep them informed at all times.
- BIdentify the stakeholders, planning, managing and monitoring their engagement
- CMeet and keep informed any people related to the project at all times
- DIdentify the stakeholders and monitor their level of satisfaction
How the community answered
(31 responses)- A87% (27)
- B3% (1)
- C3% (1)
- D6% (2)
Explanation
The most critical stakeholder management actions a project manager must take are identifying the key stakeholders and ensuring they are consistently kept informed throughout the project lifecycle. This establishes the foundation for trust, buy-in, and effective decision-making. While option B describes the full PMBOK stakeholder management process (Identify, Plan, Manage, Monitor), the question asks what a PM 'should follow,' and the exam answer emphasizes the two most essential, actionable behaviors: identification and ongoing communication. Option C is too broad (not all people related to a project need constant updates), and option D omits proactive communication.