The correct answer is B: Project baseline. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Which component of the project management plan should be updated if a change occurs?

Options

  • AProject charter
  • BProject baseline
  • CAssumption log
  • DSchedule forecast

Topics

#Change Control#Project Baselines#Project Management Plan Updates#Schedule Forecasts

Community Discussion