CAPM · Question #352
Which component of the project management plan should be updated if a change occurs?
The correct answer is B. Project baseline D. Schedule forecast. When an approved change occurs on a project, the relevant project baselines (scope baseline, schedule baseline, and cost baseline) within the Project Management Plan must be updated to reflect the newly agreed-upon parameters - baselines represent the approved version of the…
Question
Options
- AProject charter
- BProject baseline
- CAssumption log
- DSchedule forecast
How the community answered
(32 responses)- A6% (2)
- B88% (28)
- C6% (2)
Explanation
When an approved change occurs on a project, the relevant project baselines (scope baseline, schedule baseline, and cost baseline) within the Project Management Plan must be updated to reflect the newly agreed-upon parameters - baselines represent the approved version of the plan and must stay current. Schedule forecasts (project documents, not plan components) are also revised to reflect updated projections based on the change. The Project Charter (A) is not updated for individual project changes - it is a high-level authorization document. The Assumption Log (C) is only updated if the change affects project assumptions.
Topics
Community Discussion
No community discussion yet for this question.