The correct answer is B: Project baseline. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Which component of the project management plan should be updated if a change occurs?
Options
- AProject charter
- BProject baseline
- CAssumption log
- DSchedule forecast
Topics
#Change Control#Project Baselines#Project Management Plan Updates#Schedule Forecasts