CAPM · Question #35
To which knowledge area does the Collect Requirements process belong?
The correct answer is B. Scope Management. This question tests knowledge of which knowledge area the Collect Requirements process belongs to in the PMBOK framework.
Question
Options
- AQuality Management
- BScope Management
- CCost Management
- DIntegration Management
How the community answered
(19 responses)- B95% (18)
- D5% (1)
Why each option
This question tests knowledge of which knowledge area the Collect Requirements process belongs to in the PMBOK framework.
Quality Management processes focus on quality planning, assurance, and control - not on gathering stakeholder requirements.
Collect Requirements is the second process in the Project Scope Management knowledge area, sitting within the Planning process group. It involves determining, documenting, and managing stakeholder needs and requirements to meet project objectives, and its outputs - including the requirements documentation and requirements traceability matrix - directly feed into the Define Scope process.
Cost Management processes address estimating, budgeting, and controlling costs, which occur after requirements are already defined.
Integration Management processes coordinate and unify all other processes; they do not include requirements collection.
Concept tested: Collect Requirements knowledge area assignment