CAPM · Question #35

To which knowledge area does the Collect Requirements process belong?

The correct answer is B. Scope Management. This question tests knowledge of which knowledge area the Collect Requirements process belongs to in the PMBOK framework.

Predictive, Plan-Based Methodologies

Question

To which knowledge area does the Collect Requirements process belong?

Options

  • AQuality Management
  • BScope Management
  • CCost Management
  • DIntegration Management

How the community answered

(19 responses)
  • B
    95% (18)
  • D
    5% (1)

Why each option

This question tests knowledge of which knowledge area the Collect Requirements process belongs to in the PMBOK framework.

AQuality Management

Quality Management processes focus on quality planning, assurance, and control - not on gathering stakeholder requirements.

BScope ManagementCorrect

Collect Requirements is the second process in the Project Scope Management knowledge area, sitting within the Planning process group. It involves determining, documenting, and managing stakeholder needs and requirements to meet project objectives, and its outputs - including the requirements documentation and requirements traceability matrix - directly feed into the Define Scope process.

CCost Management

Cost Management processes address estimating, budgeting, and controlling costs, which occur after requirements are already defined.

DIntegration Management

Integration Management processes coordinate and unify all other processes; they do not include requirements collection.

Concept tested: Collect Requirements knowledge area assignment

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Collect Requirements#Scope Management#Knowledge Areas#PMBOK Processes

Community Discussion

No community discussion yet for this question.

Full CAPM Practice