Question

Which of the following is a category of organizational process assets?

Options

  • AGovernment standards
  • BOrganizational culture
  • CEmployee capabilities
  • DOrganizational knowledge bases

Topics

#Organizational Process Assets#OPAs#Project Environment#PMI Terminology