CAPM · Question #33
Tailoring considerations for project scope management may include:
The correct answer is A. requirements management, stability of requirements, development approach, and validation and control. This question tests knowledge of the tailoring considerations specific to Project Scope Management as outlined in the PMBOK Guide.
Question
Options
- Arequirements management, stability of requirements, development approach, and validation and control.
- BWBS guidelines, requirements templates, deliverable acceptance forms, and verified deliverables.
- Cbusiness needs, product descriptions, project restrictions, and project management plan.
- Dissues defining and controlling what is included in the project, verified deliverables, and quality reports.
How the community answered
(25 responses)- A88% (22)
- C4% (1)
- D8% (2)
Why each option
This question tests knowledge of the tailoring considerations specific to Project Scope Management as outlined in the PMBOK Guide.
The PMBOK Guide explicitly lists requirements management, stability of requirements, development approach, and validation and control as the key tailoring considerations for Project Scope Management. These factors reflect how the project's context - such as whether it uses predictive or agile methods - should shape how scope is defined and managed.
WBS guidelines, requirements templates, and deliverable acceptance forms are organizational process assets or tools, not tailoring considerations.
Business needs, product descriptions, and project restrictions are inputs to various initiating and planning processes, not tailoring considerations for scope management.
Issues defining scope, verified deliverables, and quality reports relate to outputs and monitoring activities, not to tailoring considerations.
Concept tested: Tailoring considerations for Scope Management
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok