nerdexam
PMIPMI

CAPM · Question #32

CAPM Question #32: Real Exam Question with Answer & Explanation

The correct answer is A: Formal authorization of the existence of the project. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

What is one of the main purposes of the project charter?

Options

  • AFormal authorization of the existence of the project
  • BFormal acceptance of the project management plan
  • CFormal approval of the detailed project budget
  • DFormal definition of stakeholder roles and responsibilities

Topics

#Project Charter#Project Authorization#Project Initiation

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions