The correct answer is C: Linear project management; project schedule and work breakdown structure (WBS). See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
A new project was approved by the project management office (PMO), and the scope of the project is to build a new detachable classroom. What delivery method and artifacts should the project manager use to deliver this project?
Options
- AAdaptive project management; project schedule and project backlog
- BLinear project management; project schedule and project backlog
- CLinear project management; project schedule and work breakdown structure (WBS)
- DAdaptive project management; project schedule and work breakdown structure
Topics
#Predictive methodologies#Project artifacts#WBS#Project schedule