CAPM · Question #325
A new project was approved by the project management office (PMO), and the scope of the project is to build a new detachable classroom. What delivery method and artifacts should the project manager us
The correct answer is C. Linear project management; project schedule and work breakdown structure (WBS). Building a physical structure like a detachable classroom has a well-defined, stable scope with predictable steps - making linear (predictive/waterfall) project management the appropriate delivery method. In linear PM, the primary planning artifacts are the project schedule (whic
Question
Options
- AAdaptive project management; project schedule and project backlog
- BLinear project management; project schedule and project backlog
- CLinear project management; project schedule and work breakdown structure (WBS)
- DAdaptive project management; project schedule and work breakdown structure
How the community answered
(45 responses)- A7% (3)
- B4% (2)
- C71% (32)
- D18% (8)
Explanation
Building a physical structure like a detachable classroom has a well-defined, stable scope with predictable steps - making linear (predictive/waterfall) project management the appropriate delivery method. In linear PM, the primary planning artifacts are the project schedule (which sequences and times activities) and the Work Breakdown Structure (WBS), which decomposes the total scope into manageable work packages. A project backlog is an agile/adaptive artifact used when requirements are evolving, which is not the case for a construction project. Answer C is correct because it correctly pairs the linear approach with its corresponding artifacts.
Topics