CAPM Question #325: Real Exam Question with Answer & Explanation

The correct answer is C: Linear project management; project schedule and work breakdown structure (WBS). See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A new project was approved by the project management office (PMO), and the scope of the project is to build a new detachable classroom. What delivery method and artifacts should the project manager use to deliver this project?

Options

  • AAdaptive project management; project schedule and project backlog
  • BLinear project management; project schedule and project backlog
  • CLinear project management; project schedule and work breakdown structure (WBS)
  • DAdaptive project management; project schedule and work breakdown structure

Topics

#Predictive methodologies#Project artifacts#WBS#Project schedule

Community Discussion