A project manager is newly assigned to a project. Which document can help the project manager understand the project scope?
The correct answer is A. Context diagram. A context diagram is the best tool for a newly assigned project manager to understand project scope. It visually defines the system boundary-showing what is inside the project's scope versus what is outside-and illustrates how the system interacts with external entities such as u
Question
Options
- AContext diagram
- BProcess flow diagram
- CUser interface now
- DData flow diagram
How the community answered
(45 responses)- A87% (39)
- B7% (3)
- C4% (2)
- D2% (1)
Explanation
A context diagram is the best tool for a newly assigned project manager to understand project scope. It visually defines the system boundary-showing what is inside the project's scope versus what is outside-and illustrates how the system interacts with external entities such as users, other systems, and organizations. This gives the PM a clear, high-level picture of scope boundaries immediately. A process flow diagram (B) shows how processes are executed, not scope boundaries. A user interface flow (C) focuses on screen navigation within the application. A data flow diagram (D) shows how data moves through a system. Only the context diagram is explicitly designed to communicate scope boundaries.
Topics
Community Discussion
No community discussion yet for this question.