The correct answer is A: Context diagram. See the full explanation below for the reasoning.
Project Management Fundamentals and Core Concepts
Question
A project manager is newly assigned to a project. Which document can help the project manager understand the project scope?
Options
- AContext diagram
- BProcess flow diagram
- CUser interface now
- DData flow diagram
Topics
#Project Scope#Context Diagrams#Scope Definition