nerdexam
PMIPMI

CAPM · Question #319

CAPM Question #319: Real Exam Question with Answer & Explanation

The correct answer is C: Revisit the work breakdown structure (WBS) again during execution, as the WBS can be defined at different points in the project.. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

During project planning, team members seemed clear on deliverables. However, as the project progressed deeper into the execution phase, team members expressed the need for smaller components to better understand what must be delivered. What should the project manager do?

Options

  • ASchedule additional meetings with the customer to explain the requirements for each deliverable at length.
  • BShare the project management plan with the team members again to bring them up to speed on the requirements.
  • CRevisit the work breakdown structure (WBS) again during execution, as the WBS can be defined at different points in the project.
  • DInform the stakeholders that the stakeholder register needs to be recreated, as the team does not understand the requirements.

Topics

#Work Breakdown Structure#Scope Decomposition#Progressive Elaboration#Project Execution

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions