PMIPMI
CAPM · Question #318
CAPM Question #318: Real Exam Question with Answer & Explanation
The correct answer is D: Follow organizational methodology and produce all required deliverables.. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?
Options
- AIdentify the processes and deliverables for only the current phase first.
- BDiscuss the processes and deliverables needed to meet the project objectives with the team.
- CIntegrate hybrid approach processes and deliverables to meet the short delivery time line.
- DFollow organizational methodology and produce all required deliverables.
Topics
#Predictive Approach#Project Management Plan#Organizational Process Assets#Process Tailoring
Community Discussion
No community discussion yet for this question.