nerdexam
PMIPMI

CAPM · Question #318

CAPM Question #318: Real Exam Question with Answer & Explanation

The correct answer is D: Follow organizational methodology and produce all required deliverables.. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?

Options

  • AIdentify the processes and deliverables for only the current phase first.
  • BDiscuss the processes and deliverables needed to meet the project objectives with the team.
  • CIntegrate hybrid approach processes and deliverables to meet the short delivery time line.
  • DFollow organizational methodology and produce all required deliverables.

Topics

#Predictive Approach#Project Management Plan#Organizational Process Assets#Process Tailoring

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions