CAPM · Question #305
Which tool should a project manager use to calculate cost variance for a project?
The correct answer is C. Actual cost. Cost Variance (CV) is calculated using the formula: CV = Earned Value (EV) – Actual Cost (AC). To perform this calculation, the project manager must have the Actual Cost (AC) - the real money spent on the work performed to date. Without actual cost data, CV cannot be computed…
Question
Options
- AContingency analysis
- BExpert judgment
- CActual cost
- DReview lessons learned from similar projects
How the community answered
(37 responses)- A5% (2)
- B3% (1)
- C89% (33)
- D3% (1)
Explanation
Cost Variance (CV) is calculated using the formula: CV = Earned Value (EV) – Actual Cost (AC). To perform this calculation, the project manager must have the Actual Cost (AC) - the real money spent on the work performed to date. Without actual cost data, CV cannot be computed. Contingency analysis, expert judgment, and lessons learned are useful project management tools, but none of them are inputs used to mathematically calculate cost variance.
Topics
Community Discussion
No community discussion yet for this question.