PMIPMI
CAPM · Question #305
CAPM Question #305: Real Exam Question with Answer & Explanation
The correct answer is C: Actual cost. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Which tool should a project manager use to calculate cost variance for a project?
Options
- AContingency analysis
- BExpert judgment
- CActual cost
- DReview lessons learned from similar projects
Topics
#Cost Variance (CV)#Earned Value Management (EVM)#Project Cost Management#Actual Cost (AC)
Community Discussion
No community discussion yet for this question.