PMIPMI
CAPM · Question #249
CAPM Question #249: Real Exam Question with Answer & Explanation
The correct answer is B: A diagram in which the critical path method has been applied.. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
A project manager is analyzing a few network diagrams in order to determine the minimum duration of a project. Which diagram should the project manager reference?
Options
- AA diagram in which resource optimization has been applied.
- BA diagram in which the critical path method has been applied.
- CA diagram in which a predefined series of activities has been organized.
- DA diagram which shows a combination of resource and time optimization.
Topics
#Critical Path Method#Project Duration#Schedule Management#Network Diagrams
Community Discussion
No community discussion yet for this question.