nerdexam
PMIPMI

CAPM · Question #249

CAPM Question #249: Real Exam Question with Answer & Explanation

The correct answer is B: A diagram in which the critical path method has been applied.. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A project manager is analyzing a few network diagrams in order to determine the minimum duration of a project. Which diagram should the project manager reference?

Options

  • AA diagram in which resource optimization has been applied.
  • BA diagram in which the critical path method has been applied.
  • CA diagram in which a predefined series of activities has been organized.
  • DA diagram which shows a combination of resource and time optimization.

Topics

#Critical Path Method#Project Duration#Schedule Management#Network Diagrams

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions