PMIPMI
CAPM · Question #248
CAPM Question #248: Real Exam Question with Answer & Explanation
The correct answer is A: Works with the sponsor to address internal political and strategic issues that may impact the team. See the full explanation below for the reasoning.
Project Management Fundamentals and Core Concepts
Question
What statement describes the function or responsibility of a project manager?
Options
- AWorks with the sponsor to address internal political and strategic issues that may impact the team
- BSeeks ways to develop relationships that assist the team in achieving organizational goals and objectives
- CEnsures that the project's business operations are efficient
- DProvides management oversight to/or a project's functional or business units
Topics
#Project Manager Responsibilities#Project Sponsor#Organizational Politics#Stakeholder Engagement
Community Discussion
No community discussion yet for this question.