CAPM · Question #248

CAPM Question #248: Real Exam Question with Answer & Explanation

The correct answer is A: Works with the sponsor to address internal political and strategic issues that may impact the team. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

What statement describes the function or responsibility of a project manager?

Options

  • AWorks with the sponsor to address internal political and strategic issues that may impact the team
  • BSeeks ways to develop relationships that assist the team in achieving organizational goals and objectives
  • CEnsures that the project's business operations are efficient
  • DProvides management oversight to/or a project's functional or business units

Topics

#Project Manager Responsibilities#Project Sponsor#Organizational Politics#Stakeholder Engagement