Question
Which action should the project manager take after the team finishes executing the scope?
Options
- AVerify the deliverables to ensure that they are correct and meet the customer's satisfaction.
- BAccept all the deliverables and deliver them to the customer for final acceptance.
- CConduct a joint session with the customer, sharing the deliverables, and then request approval.
- DCheck that all change requests were implemented and release deliverables to the customer.
Topics
#Verify Scope#Quality Control#Deliverable Validation#Project Process Flow