Which action should the project manager take after the team finishes executing the scope?
The correct answer is A. Verify the deliverables to ensure that they are correct and meet the customer's satisfaction.. After the team finishes executing the scope, the project manager must first verify the deliverables internally through the Control Quality process before presenting them to the customer. Verification ensures that deliverables meet the defined quality standards and are correct bef
Question
Options
- AVerify the deliverables to ensure that they are correct and meet the customer's satisfaction.
- BAccept all the deliverables and deliver them to the customer for final acceptance.
- CConduct a joint session with the customer, sharing the deliverables, and then request approval.
- DCheck that all change requests were implemented and release deliverables to the customer.
How the community answered
(30 responses)- A80% (24)
- B3% (1)
- C7% (2)
- D10% (3)
Explanation
After the team finishes executing the scope, the project manager must first verify the deliverables internally through the Control Quality process before presenting them to the customer. Verification ensures that deliverables meet the defined quality standards and are correct before formal acceptance. You cannot accept (B) or release (D) deliverables without first checking them, and conducting a joint session (C) skips the necessary internal verification step. The correct sequence is: produce deliverables → verify (Control Quality) → validate (Validate Scope with customer) → accept.
Topics
Community Discussion