nerdexam
PMIPMI

CAPM · Question #245

CAPM Question #245: Real Exam Question with Answer & Explanation

The correct answer is A: Verify the deliverables to ensure that they are correct and meet the customer's satisfaction.. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Which action should the project manager take after the team finishes executing the scope?

Options

  • AVerify the deliverables to ensure that they are correct and meet the customer's satisfaction.
  • BAccept all the deliverables and deliver them to the customer for final acceptance.
  • CConduct a joint session with the customer, sharing the deliverables, and then request approval.
  • DCheck that all change requests were implemented and release deliverables to the customer.

Topics

#Verify Scope#Quality Control#Deliverable Validation#Project Process Flow

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions