A recently hired project manager is looking for templates to use for projects on which they will work. To what category of enterprise environmental factors should the project manager refer?

The correct answer is A. Resource availability. Within the EEF categories, resource availability encompasses the tangible and intangible assets available to the project team, which can include templates, forms, and tools provided by the organization. Infrastructure (B) refers to physical hardware and facilities. Academic…

Project Management Fundamentals and Core Concepts

Question

A recently hired project manager is looking for templates to use for projects on which they will work. To what category of enterprise environmental factors should the project manager refer?

Options

  • AResource availability
  • BInfrastructure
  • CAcademic research
  • DCorporate knowledge base

How the community answered

(25 responses)
  • A
    76% (19)
  • B
    8% (2)
  • C
    12% (3)
  • D
    4% (1)

Explanation

Within the EEF categories, resource availability encompasses the tangible and intangible assets available to the project team, which can include templates, forms, and tools provided by the organization. Infrastructure (B) refers to physical hardware and facilities. Academic research (C) is an external EEF related to published knowledge. Corporate knowledge base (D) is more closely aligned with Organizational Process Assets (OPAs) than EEFs - OPAs are where templates are most formally stored, but among EEF categories, resource availability is the closest match.

Topics

#Enterprise Environmental Factors#Resource Availability#Templates#Project Resources