CAPM · Question #244
CAPM Question #244: Real Exam Question with Answer & Explanation
The correct answer is A: Resource availability. See the full explanation below for the reasoning.
Project Management Fundamentals and Core Concepts
Question
A recently hired project manager is looking for templates to use for projects on which they will work. To what category of enterprise environmental factors should the project manager refer?
Options
- AResource availability
- BInfrastructure
- CAcademic research
- DCorporate knowledge base
Topics
#Enterprise Environmental Factors#Resource Availability#Templates#Project Resources