CAPM · Question #244

CAPM Question #244: Real Exam Question with Answer & Explanation

The correct answer is A: Resource availability. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

A recently hired project manager is looking for templates to use for projects on which they will work. To what category of enterprise environmental factors should the project manager refer?

Options

  • AResource availability
  • BInfrastructure
  • CAcademic research
  • DCorporate knowledge base

Topics

#Enterprise Environmental Factors#Resource Availability#Templates#Project Resources