CAPM · Question #243
CAPM Question #243: Real Exam Question with Answer & Explanation
The correct answer is A: Lessons learned register. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
What is both an input and output of the Control Quality process and is updated as a result of this process?
Options
- ALessons learned register
- BRisk register
- CEnterprise environmental factors (EEFs)
- DRoot cause analysis
Topics
#Control Quality process#Lessons learned register#PMBOK inputs and outputs#Project documents