CAPM Question #243: Real Exam Question with Answer & Explanation

The correct answer is A: Lessons learned register. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

What is both an input and output of the Control Quality process and is updated as a result of this process?

Options

  • ALessons learned register
  • BRisk register
  • CEnterprise environmental factors (EEFs)
  • DRoot cause analysis

Topics

#Control Quality process#Lessons learned register#PMBOK inputs and outputs#Project documents