nerdexam
PMIPMI

CAPM · Question #220

CAPM Question #220: Real Exam Question with Answer & Explanation

The correct answer is C: Bottom-up estimating. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages. Which technique is the project manager using?

Options

  • AThree-point estimating
  • BParametric estimating
  • CBottom-up estimating
  • DData analysis

Topics

#Estimating techniques#Bottom-up estimating#Work packages#Cost/Duration estimation

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions