PMI
CAPM · Question #220
A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages. Which technique is the project manager using?
Sign in or unlock CAPM to reveal the answer and full explanation for question #220. The question stem and answer options stay visible for context.
Predictive, Plan-Based Methodologies
Question
A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages. Which technique is the project manager using?
Options
- AThree-point estimating
- BParametric estimating
- CBottom-up estimating
- DData analysis
Unlock CAPM to see the answer
You've previewed enough free CAPM questions. Unlock CAPM for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Estimating techniques#Bottom-up estimating#Work packages#Cost/Duration estimation