nerdexam
PMI

CAPM · Question #220

A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages. Which technique is the project manager using?

The correct answer is C. Bottom-up estimating. Bottom-up estimating works by decomposing work to the work package level, estimating each individual work package, and then aggregating (rolling up) those estimates to derive the total project estimate. This approach is highly accurate but time-intensive. It contrasts with…

Predictive, Plan-Based Methodologies

Question

A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages. Which technique is the project manager using?

Options

  • AThree-point estimating
  • BParametric estimating
  • CBottom-up estimating
  • DData analysis

How the community answered

(15 responses)
  • B
    7% (1)
  • C
    93% (14)

Explanation

Bottom-up estimating works by decomposing work to the work package level, estimating each individual work package, and then aggregating (rolling up) those estimates to derive the total project estimate. This approach is highly accurate but time-intensive. It contrasts with top-down approaches: Analogous estimating uses historical data from similar projects, Parametric estimating uses statistical relationships between variables (e.g., cost per unit), and Three-point estimating uses optimistic, pessimistic, and most likely values to calculate a weighted average.

Topics

#Estimating techniques#Bottom-up estimating#Work packages#Cost/Duration estimation

Community Discussion

No community discussion yet for this question.

Full CAPM Practice