PMIPMI
CAPM · Question #220
CAPM Question #220: Real Exam Question with Answer & Explanation
The correct answer is C: Bottom-up estimating. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages. Which technique is the project manager using?
Options
- AThree-point estimating
- BParametric estimating
- CBottom-up estimating
- DData analysis
Topics
#Estimating techniques#Bottom-up estimating#Work packages#Cost/Duration estimation
Community Discussion
No community discussion yet for this question.