CAPM · Question #219
Which of the following documents are created as part of Project Integration Management?
The correct answer is A. Project charter and project management plan. Project Integration Management contains two foundational processes whose outputs are the Project Charter (from Develop Project Charter) and the Project Management Plan (from Develop Project Management Plan). All subsidiary plans - including the communications management plan…
Question
Options
- AProject charter and project management plan
- BCommunications management plan and scope management plan
- CQuality management plan and risk management plan
- DProject scope statement and communications management plan
How the community answered
(65 responses)- A88% (57)
- B8% (5)
- C2% (1)
- D3% (2)
Explanation
Project Integration Management contains two foundational processes whose outputs are the Project Charter (from Develop Project Charter) and the Project Management Plan (from Develop Project Management Plan). All subsidiary plans - including the communications management plan, scope management plan, quality management plan, and risk management plan - are components of the project management plan and fall under their respective knowledge areas, not Integration Management directly. The project scope statement is an output of Scope Management, not Integration Management.