The correct answer is A: Project charter and project management plan. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Which of the following documents are created as part of Project Integration Management?
Options
- AProject charter and project management plan
- BCommunications management plan and scope management plan
- CQuality management plan and risk management plan
- DProject scope statement and communications management plan
Topics
#Project Integration Management#Project Charter#Project Management Plan#PMBOK Processes