CAPM · Question #219

CAPM Question #219: Real Exam Question with Answer & Explanation

The correct answer is A: Project charter and project management plan. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Which of the following documents are created as part of Project Integration Management?

Options

  • AProject charter and project management plan
  • BCommunications management plan and scope management plan
  • CQuality management plan and risk management plan
  • DProject scope statement and communications management plan

Topics

#Project Integration Management#Project Charter#Project Management Plan#PMBOK Processes